Articles

COP31

A big enough failure to force change?

Back at COP1 global mean sea levels were around 10cm lower and the global average temperature was around 0.7 Degrees C lower.  Since then we’ve reduced the percentage of earth that is forested by 3% to 32% total, and lost around 25% of our original global biodiversity.  Global fossil fuel consumption has risen by around 60% and we have emitted over 1,400,000,000,000 (1.4 trillion) tonnes of CO2 equivalent.

https://ourworldindata.org/grapher/total-ghg-emissions?tab=line&time=1995..latest&country=~OWID_WRL

Atmospheric CO2 is now at 427 parts per million, higher than it has been in roughly 3 million years.  There is no doubt that our burning of fossil fuels has caused this increase in atmospheric CO2.  The last time that atmospheric CO2 was this high was around the time when human evolution diverged from chimps.  Heat related mortality has increased by around 23%.

The daily sea surface temperature has been the highest ever recorded for the time of year consistently since the start of June and there are very valid fears for the impact of El Nino this year if it becomes supercharged.

Climate Reanalyzer

The Outcome

COP31 has failed in part due to a lack of willingness from certain countries to agree to mention fossil fuels in the text.  The chairing countries (Australia and Turkey) chose to remove the language in the hopes that bowing to fossil fuel interested countries would help to reach an accord – and to some extent for their own self-interests.  There can be no clearer indication of the farce that COP has become than the inability to agree to mention the cause of climate change.  There is already a binding agreement from COP28 for countries to transition away from fossil fuels, so to fail to agree to mention them now shows how the meet is regressing.

Electrification and climate debt were two other key items that remained unsolved as the clock ran out.  The potential positive impacts of electrification in reducing waste in the system have been addressed recently in Nature, considering how the actual flows of energy and waste rejected in the system would change with the same required useful outputs from a highly electrified system.  The primary energy input required to achieve the same useful output reduces by nearly 50%.  Electrification should have been an easy target to agree, driving to reduce waste is always good sense.

Fig. 1: Global energy flows in 2022 and in a highly electrified, renewable-supplied system delivering the same useful energy.

Rosenow, J., Eyre, N., Rissman, J. et al. The primary energy fallacy in energy transitions. npj Clean Energy 2, 38 (2026). https://doi.org/10.1038/s44406-026-00055-3

The lack of a final agreement is indicative of the strength of will in countries who do want to make progress and refused to allow the backslide of language and sentiment to be ratified.  It does however cement the fact that COP is no longer functioning.  It already had severe weaknesses in the lack of ability to hold countries to account for meeting the agreements they have signed, but now even these weakly enforceable agreements can’t be reached.

Where do we go from here?

COP32 is scheduled to take place in Ethiopia and is likely to heavily focus on the need for climate finance pledges to be fulfilled and expanded.  There needs to also be a focus on adaptation, which the overshoot we now know will occur makes more critical.  These are important items to reach a consensus on and work needs to start soon, not during the event.

Over thirty meetings in, it may be time for a rethink on how we address climate change, more work must be done outside of COP to move more easily to a signed accord during the dedicated time.  Countries who are aligned need to begin to act together regardless of the resistance of a few and the lobbying of the fossil fuel industry.  For those coalitions of countries who were open to committing to the higher impact wording, an agreement outside of COP might be fruitful.

There is a new group forming, 57 countries ready to move forwards who met for the first time this year and the 2027 conference is aiming to shift from dialogue to concrete action: 2nd Conference on the Just Transition Away from Fossil Fuels | Pacific 2027

Commercial Energy Procurement for Senior Leadership Teams

Free Webinars

I’m really thrilled to announce that in January and February we will be hosting free webinars for those responsible for purchasing gas and electricity at manufacturing companies.

The world of commercial energy procurement is very different from that of domestic.  For many employees responsible for purchasing these contracts they may only engage with it once every two years, meaning it’s just four procurement rounds since the market behaviours changed dramatically after the Beast from the East back in 2018.  Now that dramatic spike is barely visible on the long-term graph.  You can’t be expected to be an expert with such infrequent need to procure.

 

We don’t want to sell you a utility contract!

The world of energy procurement can be confusing and TPIs have their own interests which can influence how they portray different aspects of it.  Ethical Sustainability are different.  We don’t act as a broker.  We don’t uplift your unit rates. We don’t have favoured suppliers who have preferential commission payment agreements with us.

We want to upskill your teams to understand the different options available to you so you can create an energy risk management strategy that suits your organisation.  Then you can choose how to go to market and when to go to market in an informed way to achieve the best outcomes for you.

If you’re paying more than £80 MWh for your electricity commodity (before taxes and levies) in 2026/27 FY you probably got your procurement wrong this contracting round.  Lets fix it for your next contracting window, sign up below!

Name
Immediate Needs

Eii, NCC, BIS, BICS – Acronym Salad Decoded

Electricity taxes & levies, and their discount schemes, the acronyms and why the most important thing to understand is still your business.

BIS and BICS

For months, we have been resisting abbreviating the British Industrial Competitiveness Scheme as BICS, instead using BIC.  Our main driver in this was to try to limit confusion with the British Industry Supercharger, BIS, which is typically now how we refer to the Energy Intensive Industries Renewable Levy Exemption and the Network Charging Compensation Scheme.

The acronym gods have decided though and the British Industrial Competitiveness Scheme will be BICS!

Compensation vs Exemption

A compensation scheme like the NI Eii scheme or the NCC provides compensation in arrears, typically a year after your business has paid those taxes or levies.  An exemption scheme provides the cost avoidance up front, via your supplier invoicing so that you never pay them in the first place.

Both BICS and BIS provide exemptions, BIS also has a compensation element.

In Northern Ireland, there is not yet an equivalent to BICS or NCC, but the Eii scheme is the Energy Intensive Industries Compensation for the Indirect Costs of Funding the Renewable Obligation Scheme so businesses wait to receive the payments rather than seeing discounted invoicing.

NACE, SIC and HS Codes

Eligibility for all of these schemes is based on what kind of a manufacturer you are.

BIS uses NACE codes

BICS uses SIC and HS codes.

A Nomenclature of Economic Activities, or NACE code is a four-digit code uniquely identifying a specific type of economic activity.  It is a European system to classify what kind of business you are.

A Standard Industrial Classification, or UK SIC code is a five digit code, they are based directly on the nomenclature of NACE codes, excepting the final digit, which was introduced to refine further into different forms of business.

To convert between NACE and SIC, simply remove the separating “.” between the two numbers of the NACE code and add a 0.

HS Codes, or Harmonized System codes are different.  Developed by the World Customs Organisation these categorise the goods produced to enable taxing during global export.  Typically 6 digits, but with the ability to add additional sub-classifications, in the UK these tend to be 10 digits long.  It is the global system for trading and requires much more granular detail on your actual outputs, rather than your activities as a business.

The move to look at outputs not just area of activity should be seen as an indication of future direction for other schemes, and the requirement to update SIC codes which are not reflective of production outputs may open areas of challenge on other scheme eligibility.

We understand the charges and the codes for you so you can focus on what you do best.

Understanding your activities and production data, alongside your GVA is essential when assessing how best to deliver the optimum reduction in your taxes and levies as a manufacturer.  At Ethical Sustainability we work alongside you, understanding your processes and production, your plans and strategies and providing insights on how they may shift your eligibilities over time.

Contact us today to start understanding your eligibility!

5 Weeks to Go – Time Risks for BICS

Just five weeks to go until the first application window closes and access to two years of British Industrial Competitiveness Scheme benefits is lost.

Some key timeline risks you need to know about if you haven’t started yet:

  1. Six Digit Company Authentication Code – Used for filing your accounts with companies house, you should hold this on record but if you don’t you will need to apply for it to be sent to you by post to your registered address – time cost up to 10 working days.
  2. SIC Code Change – If you manufacture eligible products but don’t have an eligible SIC code listed you must add one – time cost up to 3 working days.
  3. Signed Letter from a Registered Officer – Depending on your company structure this may be no time cost at all or a significant one –  time cost around 5 working days.

Your actual timeline remaining could be only 2.5 weeks to gather your evidence!

The Evidence Pack

“Applications must be completed carefully, as there will be no opportunity to amend an application after it has been submitted.  Applications may be rejected where the evidence provided is incomplete, inconsistent, unclear, has been altered, or is insufficient to verify eligibility or the exemption claimed.”
British Industrial Competitiveness Scheme: guidance for applicants – GOV.UK

In our article here we discussed the evidence you need to submit with your application.  Gathering and labelling your production data by HS code is the top bottleneck we are seeing in building the evidence for submission.  This is the basis of any electricity use apportioning where there is a mixture of eligible and ineligible production on site.

It is crucial that you get this application right.  The benefits on the line if you are rejected due to insufficient evidence are significant.

 

If your application isn’t done yet, what’s holding you up?  Contact us now for support!

 

ESOS – A Lean Approach

As a manufacturer, have you seen any value from ESOS Phases 1-3?  Have your surveyors really understood your sites, their processes, and your key metrics of success?  Or have you received three reports with generic recommendations that couldn’t realistically be integrated into your business strategy?

Most companies captured by ESOS have office and retail spaces, and the reality is that in most cases a lead assessor working on your report and the site surveyor surveying it see the inside of a factory only ~10 times every four years.  It is crucial that when selecting your partner for this mandatory outgoing you consider whether they will treat you like a retailer, or whether they have a manufacturing-tailored ESOS process.  ESOS Phase 4 is an opportunity to do things a little differently, and drive value from the exercise.

Work with our assessors and experience a Lean informed ESOS approach.

We will not just survey your large electricity consumers , we will schedule time with your teams to involve them in finding efficiencies by running kaizen events to gather real insights from your greatest resource, your own people.  We will understand your processes in detail and where you have energy waste within them, not only where energy use can be reduced in the wider site.

Tools used in our work with you can be tailored to your specific needs but typically as a minimum we will create energy value streams showing the losses at each stage of your process, and part of your site level report will include these with a corrective measures portfolio showing how energy saving measures actually impact on your business.  It is common for us to visit your sites multiple times during this process, with the first being focussed predominantly on creating your asset register and understanding the physical site, and others being more focussed on how you utilise equipment and the energy impacts of behaviour.

Your business plans and pre-existing strategies will inform our ratings of measures and whether these are recommended and we will let you know which measures we suggest should be developed further into investment-grade audits suitable for decision-making.  The creation of these will form part of your action plan reporting which will naturally develop over our partnership with you through regular conversations.

Where necessary for your site, we can provide additional services such as training for your on site teams to establish their own ongoing procedures for continuous improvement, both through Lean and ISO lenses, and running regular events with them.

Energy waste reduction shouldn’t be a once every four years task, Contact Us to turn ESOS into a real energy reduction partnership now.

The best time to prepare your BIC application was last month!

… The next best time is now!

It’s an old idiom, but perfect in our current situation.  The British Industrial Competitiveness Scheme opened yesterday, and many businesses who are likely eligible were not prepared.  Their applications weren’t ready, and still aren’t. Worse, in many cases, eligible businesses aren’t even aware of the scheme and what they stand to miss out on if they don’t apply in the next eight weeks.

That isn’t their fault – the consultation on legislative changes still hasn’t fed back and communications about the scheme have largely been left to Sustainability Consultancies like ours and Accountants trying to ensure their clients don’t miss out.

You can’t change the past, all we can do is take decisive action as soon as you become aware.  So what do you need to prepare?

Information on your company, including your companies house number (as you must be registered to apply) and your six digit authentication code used for submitting accounts.

Applications are at Site Level, not Business Level.  So if your business is based in Northern Ireland but you have a manufacturing site in England, Scotland or Wales – it can still apply!

For each site:

  • a description of the site, what equipment is there, eligible and non-eligible activities undertaken (Site Layouts and potentially Process Flows can be used as evidence here),
  • a copy of your electricity supply contract,
  • six months of electricity invoices
  • six consecutive months, monthly production data to include your Production Orders Record, Production Logs and Quality Control Records.
  • Your calculations and/or submetering data justifying any split in electricity consumption between eligible and non-eligible production on site.

You can apply even if your SIC code isn’t eligible, as long as you can demonstrate that your electricity is used to produce eligible HS code products!

The above evidence in many cases will already be available in your organisation.  Even if it isn’t you will be able to prepare an application with our support to ensure compliance, but in some cases you may need an on-site survey prior to submission and time is running low for these.

Inaction and delay come with a price in this case – the second best time to act is NOW!

BIC – What’s New?

In two weeks time, applications for the first year of the British Industrial Competitiveness Scheme (BIC) should begin and then, in ten and a half weeks they will close.  So where are we and what are we still waiting for?

The consultation on the required legislation updates to enable BIC to happen closed a week ago, but the outcome has not yet been published.

The proposals would allow Exchequer funding to be channelled through the CfD supplier obligation to prevent implementation of BICS from increasing electricity bills for households and other non-exempt consumers.

 

“Exchequer funding received by the Low Carbon Contracts Company (LCCC) would reduce the amount that LCCC needs to recover from suppliers to fund CfD generator payments, resulting in a lower Interim Levy Rate (ILR) and lower reserve amounts than would otherwise apply. The Government intends for the first Exchequer payment to reach LCCC in time for it to be reflected in the levy from 1 April 2027, when the BICS exemption is expected to take effect. 

The Government’s minded position is that payments should be made to LCCC each quarter before the ILR is calculated. Further details will be set out by the Department for Business, Innovation, Science and Trade (DBIST) in due course. DBIST will separately publish an Impact Assessment setting out how the implementation of the BICS exemption will not lead to an increase in electricity bills for domestic consumers or non-eligible businesses.”

 

The changes are relatively minor and simple to the legislation, however they are crucial to the operation of the scheme in the above manner, to protect other companies from footing the bill:

Amendment of the Contracts for Difference (Electricity Supplier Obligations) Regulations 2014

  1. The Contracts for Difference (Electricity Supplier Obligations) Regulations 2014 are amended as follows.

Amendment to regulation 2 (interpretation)

  1. In regulation 2, in the definition of “SoS funds”, omit “(under section 154(2)(b) of the Act)”.

Amendment to regulation 5 (CFD quarterly contribution)

  1. In regulation 5, for the definition of “SoS repayment” substitute— “SoS repayment is the total amount of SoS funds that the CFD counterparty was required to repay during that period;”.

Amendment to regulation 7 (estimated cost, income and electricity supply)

  1. In regulation 7—
    1. in paragraph (1)—
      1. after “sum of” omit “any SoS repayment and”;
      2. after “estimates of” insert “any SoS repayment and”;
    2. in paragraph (2), before sub-paragraph (a) insert— “(za) the terms on which any SoS funds have been or are expected to be provided to the CFD counterparty;”.

Proposed legislative changes to support implementation of the British Industrial Competitiveness Scheme – GOV.UK

 

We know roughly how the FY2026 equivalent payment will be calculated.  However, we do not yet know when this payment will be made – the consultation and the implementation guidance both state this will be updated as soon as possible to confirm the timeline.

The one-off payment equivalent to FY2026 benefits was confirmed in the consultation on regulatory changes and scheme delivery, and we were told that:

“This payment will be proportionate in value to what businesses would have been entitled to had BICS exemptions been in operation earlier.  To ensure businesses receive support that closely mirrors this, calculations to confirm the value of payments to be received by individual businesses will use: 

  • historical estimated electricity consumption data

  • a government-set average RO, FIT and CM policy cost discount rate

  • the businesses’ banded pro-rating percentage, to ensure that payments reflect eligible electricity use.”

 

We know how the application process will work, and that 6 years of records for audit must be kept on all matters relevant to the application.

“BIST may undertake proportionate verification activity before and after exemptions are awarded, including both targeted and random checks where appropriate.”

“Businesses must retain all records and supporting evidence relating to their application for at least 6 years and make them available to the Department on request. Records must be sufficient to demonstrate eligibility and substantiate any information provided as part of the application or ongoing exemption.

Failure to maintain or provide adequate records may result in recovery action, withdrawal of support, or other appropriate compliance measures.”

We will keep monitoring the information available as the scheme matures and if you have any questions or want to know more about BIC and how it might benefit your business, please contact us.

The UN Environment Program Overshoot Report

To date, the focus on Net Zero and reducing emissions has been in pursuit of meeting the legal obligations of the Paris Agreement.  Limiting warming to 1.5°C remains the foundation of international climate policy, but we have failed in this objective, we will see global warming above 1.5°C.  This report talks about the inevitable overshoot clearly, what impact it might have, and what we now need to mobilise to achieve.  Much of the below article is simply quoted directly from the report as a summary, as it needs no further contextualisation.  Please do read the original text in it’s entirety if you can: https://www.unep.org/resources/limiting-overshoot-navigating-exceedance

 

Well below 2°C was set as our global target for good reason.  Global warming of a degree and a half is not safe, it already comes with huge implications.

  • Some locations might become more or less uninsurable, or even uninhabitable (Vanos et al. 2023; Chen and Lin 2024; Spencer et al. 2024). High-mortality summer seasons are expected to become commonplace without adaptation (Lüthi et al. 2023).
  • The effects on agriculture will drive significant productivity losses and threaten the food security and livelihoods of billions of people (FAO 2023a; FAO and WMO 2026)
  • Climate-related changes in food availability and diet quality are estimated to increase nutrition-related diseases and the number of undernourished people, affecting at least tens of millions of people, particularly among low-income households in low- and middle-income countries in sub-Saharan Africa, South Asia and Central America (IPCC 2023a)
  • Global glacier loss is projected to continue for centuries even if global warming were stabilized at current levels, and will alone lead to 9cm of sea level rise (Zekollari et al. 2025, Rounce et al. 2023)
  • Adjustments in the hydrological cycle, atmospheric circulation and major ocean circulations such as the Atlantic Meridional Overturning Circulation (AMOC) are projected to continue for centuries well after emissions have ceased (Lacroix et al. 2024).
  • Permafrost carbon losses may be irreversible, even if permafrost areas may partially recover under global warming reversal (Cui, Ji and Chen 2025)
  • Irreversible impacts on forest and other ecosystems, such as Amazon forest loss and high-latitude woody encroachment (Munday et al. 2025)
  • Increased likelihood of crossing ecological thresholds and tipping points, such as large-scale forest die-back (Meyer and Trisos | UNEP | Limiting Overshoot 2023)

The most stringent emission reduction pathways that were available around the time of the Paris Agreement are no longer feasible.  Such pathways required immediate, deep and sustained global GHG emissions reductions to start as early as 2015 or 2020.  We now need to face the consequences of our inaction and work hard to mitigate the impacts.

The above should not be interpreted as evidence that action no longer matters. It changes the pathway: from avoiding exceedance altogether to limiting how high and how long temperatures rise above 1.5°C while preserving the possibility of returning below it.  Every fraction of a degree and every year above 1.5°C increases exposure to climate hazards and the likelihood of irreversible loss (IPCC 2022a; Schleussner et al. 2024; Reisinger et al. 2025).

 

Overshoot narrows options and increases risks, costs and trade-offs. It does not eliminate the ability to limit additional harm!

The most effective risk management strategy is to reduce emissions rapidly in the near term and progress towards net zero as early as possible, thereby limiting peak warming and the duration of exceedance.  Proactive adaptation is equally essential – not only to reduce harms but also to maintain capacity to sustain mitigation efforts under the increasing pressures associated with overshoot.

Rapid and sustained mitigation within this decade is both necessary and feasible across all sectors and GHGs to hold warming well below 2°C and as close to 1.5°C as possible by the end of the century.  The challenge is to act while recognizing uncertainty, rather than waiting for uncertainty to disappear.

We must reach global net-zero CO₂ emissions in the 2050s, alongside deep reductions in other gases.

We must avoid new high-carbon assets and accelerate retirement or retrofitting of existing high-emission infrastructure.  Agriculture and Waste will be key areas for Methane reduction and Carbon Dioxide Removal is crucial but becomes more difficult at higher levels of warming, further emphasising the need to act fast.

 

Net-Zero is now only a milestone towards Net-Negative

Halting global warming at any level below 2°C already requires reaching at least net-zero CO₂ emissions globally, along with deep reductions of other GHGs, particularly methane (IPCC 2021). Reversing global temperature would rely on mitigation efforts going beyond this, to reach sustained global net-negative CO₂ emissions alongside continued further reductions in residual non-CO₂ GHGs.

Here at Ethical Sustainability we firmly believe that we can reverse our trajectory and that UK manufacturing is a crucial part of the solution.  Come talk to us about the risks and benefits your business will be exposed to by 1.5°C warming!

Electricity Purchasing

There are two elements to consider when defining your electricity contracting plan.

  1. The form of trading, duration of contract or hedging window and purchasing strategy all impact on the commodity price achieved.
  2. The supplier chosen and options defined for billing impact your non-commodity charges.

Historically a majority of manufacturers have placed fixed price contracts, for generally a short-term trading window.  Since market volatility increased these may not be the most advantageous approach to take.  A fixed price supply contract is based on suppliers assessing a suitable price on a single day of the year, then adding risk premium to cover them for potential market movement.  Many of these are placed in September for October start dates, which is typically a higher point in the market cycle – it’s very unlikely that a day in September turns out to have been the best day in the year to contract a price.

In the below graph, only 2017 and 2019 would have secured reasonable price if procured in September.  Ideally, you would have placed a long-term contract in May 2020, and extended in February 2024.  A good consultancy would have been pushing you to extend your contract horizon at those times, regardless of your purchasing method.  Contract duration should always be informed by the market and how good current pricing is!

There are a number of ways to go to market for electricity.  For small consumers, they are often stuck with fixed price, day priced contracts and can only vary duration.  Most manufacturers though, have the option to access the wholesale commodity market.  This opens up flexible contracting with a supplier – where you decide when to purchase and how much to purchase.  For some that sounds labour-intensive but you can put in place strategies and utilise a TPI to trade on your behalf based on rules you set that reflect your risk profile.  Historically many of these flexible contracts used a calendar-based trading system (a set % had to be purchased by a set date).  These worked well in a low volatility market, by averaging the cost across the year.  Now, the average is not a good price and they have typically been replaced by price and risk based trading strategies.

A footnote here to PPA procurement, which provides typically index-linked fixed pricing for a 10 year period via a complex and costly contracting arrangement.

Moving away from Commodity, the type of Non-Commodity charging is especially important for manufacturers.  With taxes and levies making up the majority of your electricity invoice, you shouldn’t just let the supplier dictate how you pay these without considering it.  Often when you go to market a supplier will suggest you fix your non-commodity charges.  It enables them and you to predict your costs simply with only your usage as a variable, and it removes a risk of rebilling for prior financial years, sounds great right?  It can be, if a charge increases it might save you from the impact of that for half a year.  But if things change dramatically, suppliers have the right to review these charges anyway, and for manufacturers there are reasons not to fix.

As large consumers you may have access to discounts on these charges, via some of the schemes we administer, and this is significantly harder to validate if your supplier has fixed your charges, or is not fully itemising them on your invoicing.  If you go to a supplier to implement Eii exemptions, and you have fixed all your charges, you have zero visibility of what they should be removing.  You also have zero way to validate that they have removed a suitable value from your costs.  For manufacturers, we recommend a pass-through style contract, and be aware that some suppliers have “pass-through” contracts which are only partially so.  You need to ask specifically for an example of the invoicing on the contract you are signing to be sure it is fully pass-through.

If you need support with your electricity contracting, our preference is to act as your advisor rather than an intermediary, but please do reach out to ask for our help!

Types of “Renewable” electricity contracts, and the risk of Greenwashing

Ethical Sustainability reporting for SECR and other disclosures is transparent and designed to be easily assure-able.  We align as far as is possible from our position with the International Ethics Standards Board for Accountants (IESBA) standards for sustainability reporting, the International Ethics Standards Board for Accountants (IESBA).  This means that when considering “renewable” electricity contracts, we want to be as careful as possible to ensure they are high quality.

The Science-Based Targets Initiative set standards for renewable generation which can be a challenge to meet via traditional supply contracting.

“Market instruments shall be limited to LCE generators commissioned or re-powered within fifteen years preceding the period of electricity consumption to which the instrument is applied.”

https://standards.sciencebasedtargets.org/

With those of the above that can meet the requirements for reporting under SBTi, you can see that the crucial thing is to ensure that your specific contract is defined in such a way to meet them – if you go into procurement without defining those needs there is a risk that you still miss them even with an expensive CPPA agreement.

Outside of choosing whether and how to reduce the carbon footprint of your Scope 2 emissions, there are other crucial considerations too, which we address in this article.

© 2026 Ethical Sustainability | Designed + Built by Studio Artemisia